{"583936":{"#nid":"583936","#data":{"type":"news","title":"Price Gilbert and Crosland Tower Renewal: November 2016 through January 2020","body":[{"value":"\u003Cp\u003E\u003Cstrong\u003ECONSTRUCTION DETAILS:\u003C\/strong\u003E\u003C\/p\u003E\r\n\r\n\u003Cul\u003E\r\n\t\u003Cli\u003EStart Date: November 1, 2016\u003C\/li\u003E\r\n\t\u003Cli\u003EAnticipated End Date: January 30, 2020\u003C\/li\u003E\r\n\u003C\/ul\u003E\r\n\r\n\u003Cp\u003E\u003Cstrong\u003ENormal Working Hours: 7am-5pm. Weekend work will only be necessary in there are major rain delays.\u003C\/strong\u003E\u003C\/p\u003E\r\n\r\n\u003Cp\u003E\u0026nbsp;\u003C\/p\u003E\r\n\r\n\u003Cp\u003E\u003Cstrong\u003E\u003Cem\u003ECampus Detours or Interruptions:\u003C\/em\u003E\u003C\/strong\u003E\u003C\/p\u003E\r\n\r\n\u003Cp\u003EPhased detours of pedestrian traffic will occur around the Library complex, corresponding the construction sequences.\u003C\/p\u003E\r\n\r\n\u003Cp\u003ENovember 2016-2017: Work will close the north sidewalk of Bobby Dodd Way between Old Civil Engineering Building, Cherry Street and the alley between Old Civil Engineering building and Crosland Tower.\u003C\/p\u003E\r\n\r\n\u003Cp\u003EJuly 2017-November 2018: Work will close described above and also pedestrian way between Bobby Dodd Way\/Cherry Street to Fourth Street between Price Gilbert and Crosland Tower. Access to Hinman and Rich will be maintained from Fourth Street but not o he north side of the Price Gilbert Library.\u003C\/p\u003E\r\n\r\n\u003Cp\u003E\u0026nbsp;\u003C\/p\u003E\r\n\r\n\u003Cp\u003E\u003Cstrong\u003ERENEWAL BENEFITS:\u0026nbsp;\u003C\/strong\u003E\u003C\/p\u003E\r\n\r\n\u003Cul\u003E\r\n\t\u003Cli\u003EImproved accessibility and\/or ADA Compliance\u003C\/li\u003E\r\n\t\u003Cli\u003EThis project is an Adaptive Reuse and meets sustainability goals\u003C\/li\u003E\r\n\t\u003Cli\u003EAdded seating and study space for students\u003C\/li\u003E\r\n\t\u003Cli\u003ENew technology tools will support learning goals\u003C\/li\u003E\r\n\u003C\/ul\u003E\r\n\r\n\u003Cp\u003E\u0026nbsp;\u003C\/p\u003E\r\n\r\n\u003Cp\u003E\u003Cstrong\u003EUSER DETAILS:\u003C\/strong\u003E\u003C\/p\u003E\r\n\r\n\u003Cp\u003EAll computers, scanners, printers, study spaces and other resources in Crosland will move to Price Gilbert, also known as Library West. More information can be found at\u0026nbsp;http:\/\/renewal.library.gatech.edu\/\u0026nbsp;\u003C\/p\u003E\r\n","summary":null,"format":"limited_html"}],"field_subtitle":"","field_summary":[{"value":"\u003Cp\u003EThe Dorothy M. Crosland Tower closed for nearly two years on December 31, 2015. Interior abatement has begun in some areas and pedestrian detours will change throughout construction phases.\u0026nbsp;\u003C\/p\u003E\r\n","format":"limited_html"}],"field_summary_sentence":[{"value":"The Dorothy M. Crosland Tower will be closed for nearly two years to undergo a complete renewal. Interior abatement has begun in some areas and pedestrian detours will change throughout construction phases.\u00a0"}],"uid":"27705","created_gmt":"2016-11-16 15:41:51","changed_gmt":"2017-01-26 19:36:56","author":"Jessica Rose","boilerplate_text":"","field_publication":"","field_article_url":"","dateline":{"date":"2016-11-16T00:00:00-05:00","iso_date":"2016-11-16T00:00:00-05:00","tz":"America\/New_York"},"extras":[],"hg_media":{"586503":{"id":"586503","type":"image","title":"LibraryNext 2017 Construction Map ","body":null,"created":"1485459233","gmt_created":"2017-01-26 19:33:53","changed":"1485459233","gmt_changed":"2017-01-26 19:33:53","alt":"Map of showing construction boundaries. ","file":{"fid":"223529","name":"LIBRARY_Construction_Map_2017.jpg","image_path":"\/sites\/default\/files\/images\/LIBRARY_Construction_Map_2017.jpg","image_full_path":"http:\/\/www.tlwarc.hg.gatech.edu\/\/sites\/default\/files\/images\/LIBRARY_Construction_Map_2017.jpg","mime":"image\/jpeg","size":533927,"path_740":"http:\/\/www.tlwarc.hg.gatech.edu\/sites\/default\/files\/styles\/740xx_scale\/public\/images\/LIBRARY_Construction_Map_2017.jpg?itok=zflYozUK"}},"585634":{"id":"585634","type":"image","title":"Library construction - January 2017","body":null,"created":"1483979397","gmt_created":"2017-01-09 16:29:57","changed":"1483979397","gmt_changed":"2017-01-09 16:29:57","alt":"","file":{"fid":"223241","name":"LIBRARY DSC_3436.jpg","image_path":"\/sites\/default\/files\/images\/LIBRARY%20DSC_3436.jpg","image_full_path":"http:\/\/www.tlwarc.hg.gatech.edu\/\/sites\/default\/files\/images\/LIBRARY%20DSC_3436.jpg","mime":"image\/jpeg","size":148694,"path_740":"http:\/\/www.tlwarc.hg.gatech.edu\/sites\/default\/files\/styles\/740xx_scale\/public\/images\/LIBRARY%20DSC_3436.jpg?itok=XsCs10RF"}},"585632":{"id":"585632","type":"image","title":"Library construction - January 2017","body":null,"created":"1483979219","gmt_created":"2017-01-09 16:26:59","changed":"1483979219","gmt_changed":"2017-01-09 16:26:59","alt":"","file":{"fid":"223239","name":"LIBRARY DSC_3425.jpg","image_path":"\/sites\/default\/files\/images\/LIBRARY%20DSC_3425.jpg","image_full_path":"http:\/\/www.tlwarc.hg.gatech.edu\/\/sites\/default\/files\/images\/LIBRARY%20DSC_3425.jpg","mime":"image\/jpeg","size":173550,"path_740":"http:\/\/www.tlwarc.hg.gatech.edu\/sites\/default\/files\/styles\/740xx_scale\/public\/images\/LIBRARY%20DSC_3425.jpg?itok=jai4wCxZ"}}},"media_ids":["586503","585634","585632"],"related_links":[{"url":"http:\/\/renewal.library.gatech.edu\/content\/building-updates","title":"Building Updates for LibraryNEXT"},{"url":"http:\/\/renewal.library.gatech.edu\/","title":"About Creating a Library of the 21st Century: LibaryNEXT"}],"groups":[{"id":"383831","name":"Facilities Management"}],"categories":[{"id":"129","name":"Institute and Campus"}],"keywords":[{"id":"5332","name":"Georgia Tech Library and Information Center"},{"id":"172733","name":"librarynext"},{"id":"35921","name":"Facilities Management"},{"id":"143221","name":"Facilities-Notices"},{"id":"143241","name":"Facilities-detour"},{"id":"10641","name":"buidling construction"}],"core_research_areas":[],"news_room_topics":[],"event_categories":[],"invited_audience":[],"affiliations":[],"classification":[],"areas_of_expertise":[],"news_and_recent_appearances":[],"phone":[],"contact":[{"value":"\u003Cp\u003EJessica Rose, Facilities Communication Officer\u003C\/p\u003E\r\n\r\n\u003Cp\u003EGary Petherick, Construction Manager\u0026nbsp;\u003C\/p\u003E\r\n","format":"limited_html"}],"email":["jrose@gatech.edu "],"slides":[],"orientation":[],"userdata":""}}}